APPENDICES TO AMC TO ANNEX II (Part-145)
Appendix II to AMC2 145.B.310(c) — EASA Form 6
ED Decision 2022/011/R
Part-145 APPROVAL RECOMMENDATION REPORTEASA FORM 6 | |
Part 1: General Name of organisation: Approval reference: Requested approval rating: EASA Form 3 dated*: FAA Title 14 CFR Part 145 Certificate No (if applicable): TCCA CAR 573 Certificate No (if applicable): ANAC RBAC 145 Certificate No (if applicable): Address of facility audited: | |
Audit period: From | to |
Date(s) of audit: Audit reference(s): Persons interviewed: | |
Competent authority inspector(s): Competent authority office: *delete as appropriate | Signature(s): Date of EASA Form 6 Part 1 completion: |
Part-145 APPROVAL RECOMMENDATION REPORTEASA FORM 6 | ||||||||||||||
Part 2: Part-145 Compliance Audit Review | ||||||||||||||
The five columns may be labelled and used as necessary to record the approval class and/or product line reviewed. Against each column used of the following Part-145 points, please either tick (√) the box if satisfied with compliance, or cross (X) the box if not satisfied with compliance and specify the reference of the Part 4 finding next to the box, or enter 'N/A' where an item is not applicable, or 'N/R' when applicable but not reviewed. | ||||||||||||||
Point | Subject | |||||||||||||
Facility requirements | ||||||||||||||
| ||||||||||||||
Personnel requirements | ||||||||||||||
Certifying staff and support | ||||||||||||||
staff | ||||||||||||||
Airworthiness |
| |||||||||||||
review staff | ||||||||||||||
Equipment and tools | ||||||||||||||
Components | ||||||||||||||
Maintenance data | ||||||||||||||
Production planning | ||||||||||||||
Performance of maintenance | ||||||||||||||
Certification of maintenance | ||||||||||||||
Record-keeping | ||||||||||||||
Occurrence reporting | ||||||||||||||
Maintenance procedures | ||||||||||||||
Maintenance organisation | ||||||||||||||
exposition (MOE) (see Part 3) | ||||||||||||||
Privileges of the organisation | ||||||||||||||
Changes to the organisation | |||||||||||||||
Findings | |||||||||||||||
Means of compliance | |||||||||||||||
Access | |||||||||||||||
Immediate reaction to a |
| ||||||||||||||
safety problem | |||||||||||||||
Management system | |||||||||||||||
Internal safety reporting | |||||||||||||||
scheme | |||||||||||||||
Contracting and | |||||||||||||||
subcontracting | |||||||||||||||
Competent inspector(s): | Signature(s): | ||||||||||||||
Competent authority office: | Date of EASA Form 6 Part 2 completion: | ||||||||||||||
| ||
Part 3: Compliance with 145.A.70 Maintenance organisation exposition (MOE) Please either tick (√) the box if satisfied with compliance, or cross (X) if not satisfied with compliance and specify the reference of the Part 4 finding, or enter 'N/A' where an item is not applicable, or 'N/R' when applicable but not reviewed. | ||
PART 1 | General | |
1.1 | Statement by the accountable manager | |
1.2 | Safety policy and objectives | |
1.3 | Management personnel | |
1.4 | Duties and responsibilities of the management personnel | |
1.5 | Management organisation chart | |
1.6 | List of certifying staff, support staff and airworthiness review staff (Note: a separate document may be referenced) | |
1.7 | Manpower resources | |
1.8 | General description of the facilities at each address intended to be approved | |
1.9 | Organisation’s intended scope of work | |
1.10 | Procedures for changes (including MOE amendment) requiring prior approval | |
1.11 | Procedures for changes (including MOE amendment) not requiring prior approval | |
1.12 | Procedure for alternative means of compliance (AltMoC) | |
PART 2 | Maintenance procedures | |
2.1 | Supplier evaluation and subcontractor control procedure | |
2.2 | Acceptance/inspection of aircraft components and material, and installation | |
2.3 | Storage, tagging and delivery of components and material to maintenance | |
2.4 | Acceptance of tools and equipment | |
2.5 | Calibration of tools and equipment | |
2.6 | Use of tooling and equipment by staff (including alternate tools) | |
2.7 | Procedure for controlling working environment and facilities | |
2.8 | Maintenance data and relationship to aircraft/aircraft component manufacturers’ instructions including updating and availability to staff | |
2.9 | Acceptance, coordination and performance of repair works | |
2.10 | Acceptance, coordination and performance of scheduled maintenance works | |
2.11 | Acceptance, coordination and performance of airworthiness directives works | |
2.12 | Acceptance, coordination and performance of modification works | |
2.13 | Maintenance documentation development, completion and sign-off | |
2.14 | Technical records control | |
2.15 | Rectification of defects arising during maintenance | |
2.16 | Release to service procedure | |
2.17 | Records for the person or organisation that ordered maintenance | |
2.18 | Occurrence reporting | |
2.19 | Return of defective aircraft components to store | |
2.20 | Defective components to outside contractors | |
2.21 | Control of computer maintenance record systems | |
2.22 | Control of man-hour planning versus scheduled maintenance work | |
2.23 | Critical maintenance tasks and error-capturing methods | |
2.24 | Reference to specific procedures | |
2.25 | Procedures to detect and rectify maintenance errors | |
2.26 | Shift/task handover procedures | |
2.27 | Procedures for notification of maintenance data inaccuracies and ambiguities | |
2.28 | Production planning and organising of maintenance activities | |
2.29 | Airworthiness review procedures and records | |
2.30 | Fabrication of parts | |
2.31 | Procedure for component maintenance under aircraft or engine rating | |
2.32 | Maintenance away from approved locations | |
2.33 | Procedure for assessment of work scope as line or base maintenance | |
PART L2 | Additional line maintenance procedures | |
L2.1 | Line maintenance control of aircraft components, tools, equipment, etc. | |
L2.2 | Line maintenance procedures related to servicing/fuelling/de-icing, etc. | |
L2.3 | Line maintenance control of defects and repetitive defects | |
L2.4 | Line procedure for completion of technical logs | |
L2.5 | Line procedure for pooled parts and loaned parts | |
L2.6 | Line procedure for return of defective parts removed from aircraft | |
L2.7 | Line procedure for critical maintenance tasks and error-capturing methods | |
PART 3 | Management system procedures | |
3.1 | Hazard identification and safety risk management schemes | |
3.2 | Internal safety reporting and investigations | |
3.3 | Safety action planning | |
3.4 | Safety performance monitoring | |
3.5 | Change management | |
3.6 | Safety training (including human factors) and promotion | |
3.7 | Immediate safety action and coordination with the operator’s ERP | |
3.8 | Compliance monitoring | |
3.8.1 | Audit plan and audit procedures | |
3.8.2 | Product audit and inspections | |
3.8.3 | Audit findings — corrective action procedure | |
3.9 | Certifying staff and support staff qualifications, authorisation and training procedures | |
3.10 | Certifying staff and support staff records | |
3.11 | Airworthiness review staff qualification, authorisation and records | |
3.12 | Compliance monitoring and safety management personnel | |
3.13 | Independent inspection staff qualification | |
3.14 | Mechanics qualification and records | |
3.15 | Process for exemption from aircraft/aircraft component maintenance tasks | |
3.16 | Concession control for deviations from the organisation’s procedures | |
3.17 | Qualification procedure for specialised activities such as NDT, welding, etc. | |
3.18 | Management of external working teams | |
3.19 | Competency assessment of personnel | |
3.20 | Training procedures for on-the-job training as per Section 6 of Appendix III to Part-66 (limited to the case where the competent authority for the Part-145 approval and for the Part-66 licence is the same) | |
3.21 | Procedure for the issue of a recommendation to the competent authority for the issue of a Part-66 licence in accordance with 66.B.105 (limited to the case where the competent authority for the Part-145 approval and for the Part-66 licence is the same) | |
3.22 | Management system record-keeping | |
PART 4 | Relationship with customer/operators | |
4.1 | List of the commercial operators to which the organisation provides regular aircraft maintenance services | |
4.2 | Customer interface procedures/paperwork | |
4.3 | [Reserved] | |
PART 5 | Supporting documents | |
5.1 | Sample documents | |
5.2 | List of subcontractors | |
5.3 | List of line maintenance locations | |
5.4 | List of contracted organisations | |
5.5 | List of used AltMoC | |
PART 6 | RESERVED | |
6.1 | [Reserved] | |
MOE Reference: MOE Amendment: Competent authority audit staff: Signature(s): Competent authority office: Date of EASA Form 6 Part 3 completion: | ||
| |||||
Part 4: Findings — Part-145 Compliance status Each finding should be recorded, whether it has been rectified or not, and should be identified by a simple cross-reference to the Part 2 requirement. All non-rectified findings should be copied in writing to the organisation for them to take the necessary corrective action. | |||||
Part 2 or 3 reference | Audit reference(s): | L E V E L | Corrective action | ||
Findings | Date Due | Date Closed | Reference | ||
|
Part 5: Part-145 Approval or continued approval or change recommendation* |
Name of organisation: Approval reference: Audit reference(s): The following Part-145 terms of approval are recommended for this organisation: Or, it is recommended that the Part-145 terms of approval specified in EASA Form 3 referenced ...................................................... should be continued. Name of recommending competent authority inspector: Signature of recommending competent authority inspector: Competent authority office: Date of recommendation: EASA Form 6 review:Date: *delete as appropriate |